Safety Delays Hammer Van Elle

Summary

Van Elle, a piling contractor, attributes a £5.5m revenue drop to building safety regulation delays. The Building Safety Act 2022 introduced stricter safety checks, causing project delays and impacting revenue. This highlights the financial consequences of enhanced building safety regulations on the construction industry.

Focus360 Energy: property compliance services – pre-planning to post-construction. Learn more.

** Main Story**

So, Van Elle, a piling contractor, has announced a £5.5 million drop in turnover – that’s about 4%. And you won’t believe what they’re blaming: delays linked to the Building Safety Act (BSA) 2022. It’s one of the first hard numbers we’ve seen showing the BSA’s real financial bite on the construction sector. Their full-year results are coming out on July 23rd, so we’ll get the full story then. But even so, it’s a pretty telling sign, isn’t it?

Delays Everywhere

According to their trading update, they’re seeing “subdued activity levels and widespread delays” because of these BSA approval holdups. Honestly, I’m not surprised; the news is full of similar stories. Van Elle says over 40 projects are affected! These projects are now pushed back to next year and the biggest issues come from “gateway 2” approvals. Now, if you don’t know, this is that crucial step before you can even start building anything over 18 meters or seven stories. It’s causing a huge logjam.

What’s the BSA All About, Anyway?

The BSA 2022 came about in response to the Grenfell Tower tragedy, aiming to make high-rise buildings much safer in England and Wales. It’s all about making sure these buildings are safe throughout their entire lifecycle.

  • The Gateway System: Think of it as three checkpoints: planning, pre-construction, and before anyone moves in. Gateway 2, that’s the sticking point. It’s where the Building Safety Regulator needs to sign off before you can lay a single brick on a high-risk building. But are there enough inspectors to cover all projects? Seems not.
  • Higher-Risk Buildings (HRBs): Basically, if it’s residential, over 18 meters, or has seven or more stories, it’s under the microscope. They’re facing much stricter rules, and rightly so, you might argue.
  • Who’s Responsible?: The act makes it clear who’s in charge at every stage, hoping to prevent those “it wasn’t my job” situations. Finally.
  • The ‘Golden Thread’: This is like a complete safety record for the building, from design to demolition, available to all. Keeping track of everything is the key to prevention, after all.

Knock-On Effects

These BSA delays aren’t just annoying. They’re having a serious ripple effect throughout the entire construction industry. Can you imagine the strain?

  • Money Troubles: Contractors are racking up extra costs, waiting for approvals, and potentially facing penalties if they don’t comply. It’s a financial headache.
  • Project Stalled: Gateway 2 is causing major bottlenecks, messing with project timelines and pushing back completion dates. Clients are understandably getting antsy.
  • Supply Chain Chaos: Subcontractors and suppliers are stuck in limbo, not knowing when projects will actually start. It’s hard to keep prices locked in when you don’t know if a project is 6 months or 2 years away from starting.
  • Housing Crisis: Delays in building high-rise apartments are making the housing shortage worse, especially in cities where we need these buildings most. No good!

So, What’s the Fix?

Honestly, it’s going to take everyone working together – industry people and regulators. Maybe some of these ideas could help.

  • Speed Things Up: We need clearer guidelines and faster reviews to get these approvals moving. No more waiting months for a simple query.
  • Talk More: Better communication between developers, designers, and the Building Safety Regulator could smooth things out. It’s not just about ticking boxes, it’s about working together.
  • Take It in Stages: What if we could submit design information in phases, rather than all at once? It might let us spot potential problems earlier. That said, I can imagine problems this approach might also cause.

The BSA is aiming for safer buildings, which is vital. But we need to figure out these approval bottlenecks to avoid damaging the construction industry and further delaying housing delivery. If we do this wrong, the whole industry suffers.

10 Comments

  1. Given the bottleneck at Gateway 2 approvals, what specific measures could the Building Safety Regulator implement to expedite the review process without compromising thoroughness?

    • That’s a great question! I agree that expediting the review process is essential. Perhaps the Building Safety Regulator could implement a triage system based on project complexity, allocating resources accordingly. Investing in AI-powered review tools to identify potential issues could also accelerate approvals without sacrificing thoroughness. What are your thoughts?

      Editor: FocusNews.Uk

      Thank you to our Sponsor Focus 360 Energy

  2. Van Elle’s experience highlights the tangible financial impact of regulatory delays. It would be useful to understand how other contractors are adapting their business models to mitigate these risks and ensure project viability under the BSA.

    • That’s a great point! Understanding how different contractors are adapting is crucial. I’ve heard some are investing in specialized BSA compliance teams and software to streamline their submissions. It would be interesting to compare strategies and see what’s proving most effective in navigating the new regulatory landscape. Has anyone else seen innovative approaches?

      Editor: FocusNews.Uk

      Thank you to our Sponsor Focus 360 Energy

  3. Van Elle’s experience underscores the importance of proactive risk management. Exploring alternative construction methods that inherently align with BSA requirements could minimize delays and improve project predictability. Has anyone seen specific design approaches or material choices effectively streamlining the approval process?

    • That’s a great point about proactive risk management! Exploring alternative construction methods seems key. I’m curious if anyone has experience with modular construction and how it aligns with BSA requirements. Streamlining through design choices could be a game-changer. What innovative materials are being used to improve safety while accelerating approvals?

      Editor: FocusNews.Uk

      Thank you to our Sponsor Focus 360 Energy

  4. The impact on subcontractors and suppliers highlights a critical vulnerability. Exploring strategies for mitigating supply chain disruptions, such as diversified sourcing or collaborative forecasting, seems essential for maintaining project momentum amidst BSA-related delays.

    • You’re absolutely right about the vulnerability of subcontractors and suppliers! Diversified sourcing and collaborative forecasting are definitely key strategies. It’s also worth considering how technology can facilitate better communication and visibility across the supply chain to minimize disruptions. Perhaps a centralized digital platform?

      Editor: FocusNews.Uk

      Thank you to our Sponsor Focus 360 Energy

  5. The “Golden Thread” concept seems crucial for long-term accountability. How can technology, like blockchain, enhance the integrity and accessibility of this data throughout a building’s lifecycle, ensuring consistent safety standards?

    • That’s a fantastic point about the Golden Thread! Blockchain’s potential to create an immutable and transparent record is definitely worth exploring. Imagine the ease of auditing and tracking changes throughout a building’s life. What other technologies could complement blockchain for enhanced building safety?

      Editor: FocusNews.Uk

      Thank you to our Sponsor Focus 360 Energy

Leave a Reply to FocusNews.Uk Cancel reply

Your email address will not be published.


*